ENERGY AUDIT REPORT OF CESU

 

MAY - 2010

 

 

 

 

 

 

 

                                                                                                        BY - ENERGY AUDIT CELL

                                                                                                         9TH FLOOR, CESU HQ, IDCO TOWER

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                                                                                                                


 

 

 

 

 

 

 

 

Energy audit is vital for all Distribution sector to find out the loss pocket & measures to curb the same to be a viable utility.

 

 

 

          CESU is conducting energy audit in 33kv feeder, 11kv feeder & in distribution transformers. The losses beyond the possible limit in HT & LT are being taken care by the meter checking squad & field unit to reduce the same.

 

The Details are

 

1-      Apex. vs. 33kv feeder Energy audit.  Energy audit done -9 nos.  Out of 27 nos. of Grid substation.

 

 2- 33kv feeder Energy Audit.  Energy audit done – 57 nos.  Out of 109 nos. of 33kv fdr

 

3- 33kv feeders having 33kv consumers meter reading from MAR-10 to MAY-10.  Energy audit done 14 nos.  Out of 39.

 

 4- Energy audit of 33kv feeders having loss ore then 10%. - 2 no’s.

                                   

5- 11kv Energy audit of BCDD-I - 1

 

6- Abstract of Energy audit done.    

 

7-33KV & 11KV assumption sheet.

 

 

    1- 33 KV Feeder Energy Audit                              

 

      i-      Total nos of 33kv feeder under CESU                = 109

ii-     Dedicated feeder                                                 = 6 ( Chilika – Balugaon Grid,  Railway – Angul Grid

                                                                                            Bajarangiwali alloy- choudwar grid,    Ipisteel, Opl, scaw - Gundichapada grid

Iii-    Line under disconnection                                    = 1 (Jagannath Spinning Mill)

iv-   Stand by                                                               = 1 ( Nimapada )

V-    Energy Audit to be done                                       = 100+6 (Dedicated) =106

Vi-   Energy Audit done                                               = 57

            Vii- Steps are being taken to bring rest 52 nos.

     feeders in to energy audit scheme.

Viii- Meter status of 33kv feeder                               = 30 Defective 33kv feeders.

 

A-11 KV Feeder Energy Audit

 

1-Total nos 11kv feeder   = 606

           

           2- Meter status of 11kv feeder = 140 Defective 11kv feeders

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Click upon the following to view the sheets

 

ENERGY LOSS IN 132 KV & 33KV GRID SUBSTATION OF CIRCLES FOR THE MONTH OF MAY 10

 

ENERGY AUDIT OF 33 KV FEEDERS OF ELECTRICAL CIRCLE UNDER CESU FOR THE MONTH OF MAY 10

 

ENERGY AUDIT OF 33 KV FEEDERS UNDER CESU HAVING LOSS MORE THAN 10% FOR THE MONTH MAY 10

 

33 KV FEEDER METER READING WITH 33 KV CONSUMERS OF CIRCLES UNDER CESU FOR THE MONTH OF MARCH 10 TO MAY 10

 

ENERGY AUDIT OF 11 KV FEEDERS FOR THE MONTH OF MAY 10

 

ABSTRACT