The metering of the 650 nos. of large &
medium industial Consumers are being regularly monitored through AMR in
major part of CESCO.. |
|
GSM technology has been adopted to download data
of all tamper prone industries from Central AMR Cell. Again with the
installation of Intelligent modem we are able to get SMS of any kind of
mishandling of metering installation. |
|
The Movement of our MRT Team became more
specific and Target oriented as many installation can be filtered sitting
at the base station itself. |
|
In the process meter tampering and bypassing has
been substantially reduced .Subsequently input has been reduced and billing
increased. |
|
Introducing on line generation of all HT Bills
through this AMR without any manual intervention soon. |
|
Intelligent AMR is being introduced which
shall send SMS to the assigned
authority on occurrence of
tampering. |
|
Investment / Expenditure |
|
One Time: Total Investment of Rs.84.1 Lakhs. |
|
Recurring Monthly: Rs.225 / installation (GSM
Service charge). |
|
Financial Gain |
|
Every month gain of collection (As penalty for
Pilferage)of Rs.1 Crore. |
|
|
|
|
|
|
Feeder Metering |
|
491 Nos. of HTTV Meters have been procured for
100% metering of 33KV and 11KV feeders. |
|
Substation Metering |
|
5600 Nos. of LTTV Meters have been procured for
distribution Sub-Station metering. |
|
2330 Meters have already been installed. |
|
Sub-Stations metering in Bhubaneswar, Cuttack
and Puri Towns are almost complete. |
|
Sub-Stations metering work at other Dist. HQs
are in progress. |
|
Cost of the project |
|
15 Crores |
|
Benefits |
|
Energy accounting and Auditing |
|
Identify loss and theft prone areas |
|
Enforcement |
|
Plot and study load profile and achieve load
balancing |
|
|
|
|
CESCO has procured 2000Km of LT XLPE AB cable of different sizes for
re-conductoring bare LT Lines. |
|
450 Kms of conductors have been delivered at
Central Store. |
|
Re-conductoring work is in progress in Bhubaneswar, Cuttack,
Dhenkanal & Paradip Circle.. |
|
|
|
Cost of the Project |
|
One Time: Total Investment of Rs.10 crores. |
|
|
|
Advantages |
|
Reduction of both commercial and as well as
technical losses. |
|
Improvement of peak load voltage. |
|
Prevention of direct hooking from LT overhead
line |
|
|
|
|
All 19 Divisions of CESCO’s bill processing is
being done at one place at CBC with one common billing software. |
|
All input data from divisions like spot billing
machine data,collection and change data is collected at CBC and after
processing the output data for SBM is handed over to the division for next
cycle billing through SBM. |
|
By keeping data centrally,data security and data
integrity is maintained. |
|
Central Billing Cell acts as DRM center of
CESCO. |
|
Billing Software as well as data is in Fox Pro
base and arrangement is being made to migrate to Oracle platform. |
|
100% Billing of all categories of Consumers are
being made In-house. |
|
Saving of Rs 4 lakhs every month in comparison
to billing by outside agency. |
|
|
|
|
|
|
Customer indexing , tagging & mapping. |
|
|
|
Data
resources Management Center (DRMC) |
|
|
|
Billing
Solution. |
|
|
|
Customer information Portal (MIS) |
|
|
|
Electricity call center and customer service center is being
setup. |
|
|
|
Energy
Audit . |
|
|
|
|
|
|
Simputers |
|
RFID (radio Frequency Identification) |
|
Collection Machine with Smart Card |
|
Auto Collection Machine (Similar to ATM ) |
|
Intelligent AMR |
|
SCADA |
|
|
|
|
|
|
|
|
Personalized RFID Smart Label to be pasted on
each meter (old existing meter). |
|
|
|
Every personalized meter will be read with
a
portable RFID Reader/writer. |
|
|
|
The meter reading will be captured. |
|
|
|
Bill
printing at the CESCO billing office or on the spot. |
|
|
|
|
|
|
|